TARIFFS OF THE ELECTRICITY DISTRIBUTION SYSTEM SERVICES
More
ELECTRICAL SAFETY
More
NEW CONNECTION AND LOAD CHANGES
More
    Investments
    2017
    Investments in grid development - 106 million euro

    This year throughout Latvia planned:

    • renewing a total of 879 km of medium-voltage power lines
    • renewing a total of 890 km of low-voltage power lines
    • reconstructing or constructing 711 transformer substations
    • clean power line routes at a length of 5 500 km

    Kurzeme

     

    This year planned:

    • renewing a total of 166 km of medium-voltage power lines
    • renewing a total of 81 km of low-voltage power lines
    • reconstructing or constructing 97 transformer substations
    Zemgale

     

    This year planned:

    • renewing a total of 112 km of medium-voltage power lines
    • renewing a total of 104 km of low-voltage power lines
    • reconstructing or constructing 85 transformer substations
    Riga

     

    This year planned:

    • renewing a total of 4 km of medium-voltage power lines
    • renewing a total of 29 km of low-voltage power lines
    • reconstructing or constructing 21 transformer substations
    Riga region

     

    This year planned:

    • renewing a total of 135 km of medium-voltage power lines
    • renewing a total of 198 km of low-voltage power lines
    • reconstructing or constructing 156 transformer substations
    Vidzeme

     

    This year planned:

    • renewing a total of 197 km of medium-voltage power lines
    • renewing a total of 201 km of low-voltage power lines
    • reconstructing or constructing 162 transformer substations
    Latgale

     

    This year planned:

    • renewing a total of 228 km of medium-voltage power lines
    • renewing a total of 156 km of low-voltage power lines
    • reconstructing or constructing 88 transformer substations